BUILDING NEWS

RBC CentreCommuniqué # 32
Weeks of June 1 to June 30, 2009

Over the next few weeks the construction activities that will take place around the development of the RBC Centre is as follows:
  • On June 1 the parking garage, PATH, and ground floor lobby areas will be opened to the public.
  • Installation of the access flooring in the typical office floor areas will proceed on levels 38, 39, 40 and 41.
  • Ground floor lobby work will be completed.
  • Lantern gutter installation will be completed
  • Street level soffits and canopies will be completed.
  • Landscaping work will continue on the west side of the property.
  • Installation of exterior lighting will start.